    Project overview

    Situation

    Weihenstephan is electrifying its truck fleet at the Freising logistics centre and needed a high-power, grid-friendly depot that integrates the existing PV system.

    Solution

    Delta Charge built a charging and energy depot: ceiling-mounted high-power chargers fed by a modular battery, coupled with on-site PV and AI-driven energy management.

    Result

    The depot is live. Weihenstephan is one of the first major German breweries operating a battery-backed DC-Fast-Charging hub, at total cost below diesel.

    System configuration

    Phase 1 · in operation

    125 kW

    Storage power

    257 kWh

    BESS

    Full build-out · modular

    375 kW

    Storage power

    771 kWh

    BESS

    High-power charging

    2× 150 kW, ceiling-mounted

    PV

    380 kWp, integrated

    Energy management

    AI-driven

    Prof. Dr. Josef Schrädler, Director, Bavarian State Brewery Weihenstephan

    „Electrifying our fleet is a concrete step on our path to decarbonisation."

    - Prof. Dr. Josef Schrädler, Director, Bavarian State Brewery Weihenstephan