Charging & energy depot · Freising-Weihenstephan logistics centre
Bayerische Staatsbrauerei Weihenstephan
One of Germany's first breweries with a battery-backed high-power truck charging hub, at total costs below diesel.
- Project type
- Hybrid BESS
- Financing
- Leasing with buy-out option

Project overview
Situation
Weihenstephan is electrifying its truck fleet at the Freising logistics centre and needed a high-power, grid-friendly depot that integrates the existing PV system.
Solution
Delta Charge built a charging and energy depot: ceiling-mounted high-power chargers fed by a modular battery, coupled with on-site PV and AI-driven energy management.
Result
The depot is live. Weihenstephan is one of the first major German breweries operating a battery-backed DC-Fast-Charging hub, at total cost below diesel.
System configuration
Phase 1 · in operation
125 kW
Storage power
257 kWh
BESS
Full build-out · modular
375 kW
Storage power
771 kWh
BESS
High-power charging
2× 150 kW, ceiling-mounted
PV
380 kWp, integrated
Energy management
AI-driven
„Electrifying our fleet is a concrete step on our path to decarbonisation."
Planning a similar site?
We plan, finance, build and operate battery-backed charging for fleets and industrial sites.